POC: Daniel S. Schwartz LAST UPDATED: 2003/02/12 20:13 EST
Manager of Marine Operations
University of Washington
School of Oceanography
Box 357940
Seattle, WA 98195-7940
Tel: 206-543-5062
Fax: 206-543-6073
Email: schwartz@ocean.washington.edu
R/V Thomas_G._Thompson 2002 FINAL Schedule
=======================================================================
All users of this Schedule are encouraged to read the notes that appear
below some of the entries to fully understand allocations of operational
days.
=======================================================================
DAYS/AGENCY/
CRUISE MAP INDEX/AREA/ P.I./INSTITUTION/ PORTS STATUS/
DATES PURPOSE PROPOSAL NO. CLEARANCE
=======================================================================
01 JAN NP9/Alongside/Seattle/ Schwartz,D/UW/ Seattle 31(Non-Op)/
31 JAN Layup/Maintenance n/a Seattle Other/
Continuation of Layup from 18 Nov. 2001.
----------
01 FEB NP9/Puget Sound/ Schwartz,D/UW/ Seattle 29(Non-Op)/
01 MAR Shipyard n/a Seattle PRV/
Shipyard Availability: ABS, Z-Drives & install new multi-beam sonar
----------
02 MAR NP9/Puget Sound/NE McDuff,R/UW/ Seattle 2/STATE/F
03 MAR Pa/Student Instruction 74-0369 Seattle
Bio 203 (Lessard)
----------
05 MAR NP9/Puget Sound/ McDuff,R/UW/ Seattle 4/STATE/F
08 MAR Student Instruction 74-0369 Seattle
Ocean 101 (T. Emerick)
----------
09 MAR NP9/Juan de Fuca/ Schwartz,D/UW/ Seattle 3/STATE/F
11 MAR Student Instruction 74-0369 Seattle
training/commission new multibeam system.
----------
14 MAR NP9/Alongside/Puget Schwartz,D/UW/ Seattle 2(Non-Op)/
15 MAR Sound/USCG Inspection n/a Seattle Other/
Annual U.S. Coast Guard Inspection
----------
24 MAR NP9/Puget Sound/ McDuff,R/UW/ Seattle 7/STATE/F
30 MAR Student Instruction 74-0369 Seattle
Ocean 443 (Holmes)
----------
09 APR NP9/Puget Sound/ McDuff,R/UW/ Seattle 4/STATE/F
12 APR Student Instruction 74-0369 Seattle
Ocean 210 (Sternberg)
----------
22 APR NP9/Juan de Fuca/ McDuff,R/UW/ Seattle 5/STATE/F
26 APR Student Instruction 74-0369 Seattle Canada
multibeam mapping
----------
03 MAY NP9/Puget Sound/ McDuff,R/UW/ Seattle 5/STATE/F
07 MAY Student Instruction 07-0369 Seattle
Mar. Bio. 351 (R. Keil)
----------
15 MAY NP9/Juan de Fuca/ McDuff,R/UW/ Seattle 9/STATE/F
23 MAY Student Instruction 74-0369 Seattle Canada
multibeam mapping (D. Kelley)
----------
27 MAY NP9/West Coast/ Barth,J/OSU/ Seattle 13/NSF/F
20 JUN GLOBEC COP G1099-054 Seattle
NP9/West Coast/ Cowles,T/OSU/ 12/NSF/F
GLOBEC OCE00001035
1st GLOBEC Cruise. SeaSoar and Marine Mammals. Coordinated with R/V Wecoma.
----------
21 JUN NP9/Puget Sound/ McDuff,R/UW/ Seattle 4/STATE/F
24 JUN Student Instruction 74-0369 Seattle
PRISM
----------
28 JUN NP9/Juan de Fuca Ridg/ Embley,B/ Seattle 49/NOAA/F
15 AUG VENTS/NeMO & Groundfis NOAA/PMEL/tbd Astoria/Por Canada
ROPOS ROV Ops. Includes transits and mobe / de-mobe of ROPOS.
----------
16 AUG NP9/NE Pacific/ Weingart,J/ Portland 57/NAVY/F
11 OCT ARDENT-01 JHU/APL/tbd San Diego
Includes 8 days mobe, 5 days de-mobe & transits.
----------
12 13 14 15
16 OCT NP9/NE Pacific/ Duennebier,Garcia/ San Diego 13/NSF/F
22 OCT Transit to Hawaii OCE-9818793/972989 Honolulu
23 24
4 days in port to mobilize JASON. 8 days transit, 2 in-port days to mobilize
science.
----------
25 OCT NP13/Hawaii/ Duennebier,F/UH/ Honolulu 3/NSF/F
12 NOV JASON Ops. OCE9818793 Honolulu
NP13/Hawaii/ Garcia,M/UH/ 16/NSF/F
JASON Ops OCE9729894
JASON Ops: 2 days F. Duennebier (OCE9818793) 13 days M. Garcia (on OCE9729894),
2 days round trip transit to site--one assigned to each PI, and 2 days in port
to de-mobe the ROV. Personnel change-out at/off Kona. Total equals 19 days.
(End date and de-mobe extended one day at request of PI, approved by NSF
10/21/02.)
----------
13 NOV NP13/Cent. Pacific/ n/a/n/a/ Honolulu 14/NSF/F
26 NOV Transit to Guam tbd Apra
27 28
29 NOV NP10/Guam/ Tivey,M/WHOI/ Apra 35/NSF/F
11 JAN JASON Ops. OCE-0099327 Apra
12
42 Science Days and 5 intra-mission transit days originally requested for 47
days total--35 in CY-2002 and 12 Days in CY-2003. After consultations
10/21/02, breakdown now is: 2 port days on arrival--11/27 and 11/28 (mobe
DSL-120.) Science Ops Days from 11/29/02 to 1/11/03 (44 days total at seat).
Arrival day, in port on the 11th and the 12th will be the de-mobe days. Grand
total comes out to 47 days: 35 in CY-'02 and 12 in CY-'03.
----------
?? ??? NP9/Puget Sound/ McDuff,R/UW/ Seattle 2(Non-Op)/
?? ??? Student Instruction 74-0369 Seattle STATE/F
(Will be carried-over into 2003.)
----------
Agency Funded Proposed TOTAL
------ ------ -------- -----
NAVY 57.0 0.0 57.0
NOAA 49.0 0.0 49.0
NSF 106.0 0.0 106.0
STATE 43.0 0.0 43.0
------ ----- ----- -----
TOTAL 255.0 0.0 255.0